The following activities represent a high - level view of the Aerocomp project. A project network needs to be developed. All times are in weeks.
The following activities represent a highlevel view of the Aerocomp project. A project network needs to be developed. All times are in weeks.
Activity Immediate Time
Predecessors
A
B A
C A
D B C
E C
F C
G E
H E F
I D G H
Develop a more detailed project plan, identify alternative project completion dates, and
recommend an optimal project deadline.
Prepare a manual PERTCPM analysis. Include an Activities Listing Table, a PERTCPM
Network Diagram that displays the critical path, and a Critical Activites Analysis Table.
Prepare a report with the Background of this project, the project deadline Issue to be
resolved, the three project deadline Alternatives, an Analysis of the three Alternatives, and a
Recommendation. Also include a Gantt Chart.
Attached to the report should be an Activities Listing Table, PERTCPM Network Diagram,
a Critical Activities Analysis Table, a Gantt Chart, and a COMPLETE PROJECTLIBRE
SOLUTION TO THIS CASE. provide me teh background, alternatives, crashing and recommendations to this case
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started