Activity Immediate Time
Predecessors
A 3
B A 1
C A 2
D B, C 3
E C 5
F C 3
G E 7
H E, F 5
I D, G, H 8
Develop a more detailed project plan, identify alternative project completion dates, and
recommend an optimal project deadline.
Prepare a manual PERT/CPM analysis. Include an Activities Listing Table, a PERT/CPM
Network Diagram that displays the critical path, and a Critical Activites Analysis Table.
Prepare a report with the Background of this project, the project deadline Issue to be
resolved, the three project deadline Alternatives, an Analysis of the three Alternatives, and a
Recommendation. Also include a Gantt Chart.
Attached to the report should be an Activities Listing Table, PERT/CPM Network Diagram,
a Critical Activities Analysis Table, a Gantt Chart, and a COMPLETE PROJECTLIBRE
SOLUTION TO THIS CASE. provide me teh background, alternatives, crashing and recommendations to this case

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Retailing Management

Authors: Michael Levy, Barton Weitz, Dhruv Grewal

9th Edition

0077512375, 9780077512378

More Books

Students also viewed these General Management questions

Question

Solve for x. 1. 2. 3. 4. = 2 = 20

Answered: 1 week ago