The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester project. C,7 E,2 D,5 F , 6
The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester project. C,7 E,2 D,5 F , 6 a. Determine the earliest start time for activity F. Earliest start time b. If the latest time activities E and F are to be finished is 13, determine the latest finish time for activity C. Latest finish time c. What is the slack for each activity? Activity Slack C D E F