The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a
Fantastic news! We've Found the answer you've been seeking!
Question:
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/06/667b8ff8145ad_815667b8ff7f41b5.jpg)
The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester project.
a. Determine the earliest start time for activity F.
b. If the latest time activities E and F are to be finished is 13, determine the latest finish time for activity C.
c. What is the slack for each activity?
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/06/667b8ff8555f8_816667b8ff844a07.jpg)