The following are the cash flows of two projects: Year Project A Project B 0 $250 $250 1 130 150 2 130 150 3 130
The following are the cash flows of two projects: |
Year | Project A | Project B |
0 | $250 | $250 |
1 | 130 | 150 |
2 | 130 | 150 |
3 | 130 | 150 |
4 | 130 | |
a. | Calculate the NPV for both projects if the discount rate is 10%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) |
Project | NPV |
A | $ |
B | $ |