Question
1 Approved Answer
The following are the cash flows of two projects: Year Project A Project B 0 $360 $360 1 190 260 2 190 260 3 190
The following are the cash flows of two projects:
Year Project A Project B
0 $360 $360
1 190 260
2 190 260
3 190 260
4 190
a. Calculate the NPV for both projects if the discount rate is 12%. Round 2 decimal places