Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The following case presents a real project ( in aggregate form ) that allows the student to compare the critical path solution approach for both

The following case presents a real project (in aggregate form) that allows the student to compare the
critical path solution approach for both completion time and cost as well as a simulated solution for time
variability and then also for both time and cost variability. The student should better understand the risk
of projects running late and over budget after this exercise.
Wesley James had recently arrived in Boston from Manchester, UK for a position as Project Owner at
NutriStar Energy, Inc. He was now meeting with Ava Smith, President of NutriStar, to discuss his
upcoming duties and responsibilities associated with their latest product, the NutriSports Energy Bar.
As Ava explained: NutriStar produces a line of vitamins and nutritional supplements. We recently
introduced our NutriSports Energy Bar, which is based on new scientific findings about the proper
balance of macronutrients in the body. Fortunately, the energy bar has quickly become popular among
elite athletes and others who focus on eating an optimal balance of macronutrients. One distinguishing
feature of the NutriSports Energy Bar is that each bar contains 50 milligrams of eicosapentaenoic acid
(EPA), a substance strongly linked to reducing the risk of cancer but found in only a few foods, such as
salmon. We were able to include EPA in our sports bars because we had previously developed and
patented a process to refine EPA for our line of fishoil capsules.
Because of the success of the NutriSports Energy Bar in the United States, we are considering offering
it in Latin America. With our domestic facility currently operating at capacity, we have decided to
investigate the option of adding approximately 10,000 square feet of production space to our facility in
Latin America, at a cost of $5.1 million.
This is where you come in, Wesley. The project to expand the Latin American facility involves four major
phases: (1) concept development, (2) definition of the plan, (3) design and construction, and (4) startup
and turnover. During the concept development phase, a project owner, that will be you, is chosen to
oversee all four phases of the project and given a budget to develop a plan. The outcome of the concept
development phase consists of just a rough plan, feasibility estimates for the project, and a rough
schedule. Also, a justification for the project and a budget for the next phase will be needed.
In the plan definition phase, the project owner selects and works with a project manager to oversee the
activities associated with this phase. Plan definition consists of four major activities that are completed
more or less concurrently: (1) defining the project scope, (2) developing a broad schedule of activities,
(3) developing detailed cost estimates, and (4) developing a plan for staffing. The outputs of this phase
are combined into a detailed plan and proposal for management specifying how much the project will
cost, how long it will take, and what the deliverables are.
If the project gets managements approval and provides the appropriations, the project progresses to
the third phase, design and construction. This phase consists of four major activities: (1) detailed
engineering, (2) mobilization of the construction employees, (3) procurement of production equipment,
and (4) construction of the facility. Typically, the detailed engineering and the mobilization of the
construction employees are done concurrently. Once these activities are completed, construction of the
facility and procurement of the production equipment are done concurrently. The outcome of this phase
is the physical construction of the facility.
The final phase, startup and turnover, consists of four major activities: prestartup inspection of the
facility, recruiting and training the workforce, solving startup problems, and determining optimal
operating parameters (called centerlining). Once the prestartup inspection is completed, the workforce
is recruited and trained at the same time that startup problems are solved. Centerlining is initiated upon
the completion of these activities. The desired outcome of this phase is a facility operating at design
requirements.
The cost to complete an activity depends on both the amount of time required to complete the task
and the cost rate of performing the activity. I have compiled two tables here for you. Table A provides
optimistic, most likely, and pessimistic time estimates for the major activities. Table B provides similar
estimates for the cost rates to complete the activities. Like time estimates, the cost rate to complete the
facility expansion project can vary for a number of reasons such as using more or less expensive
resources, price changes in labor and materials, the need to outsource work that was expected to be
performed inhouse, and so on.
Questions
1-Draw a network diagram for this project
2-. Identify all paths through the network diagram. Identify which path you expect to be the critical path and its expected completion time? 3- which paths are most likely to threaten this path in terms of becoming critical ?4-simulate the completion of this project 1,000 times assuming that activity times follow a PERT distribution. 5- Estimate the mean and standrad deviation of the project completion time and the project cost. 6- develop histograms for both the project completion time and the cost to complete the project. what do these histograms tell you ?7- Using the results of your simulation analysis, A- calculate the probability that the project can be completed in 30 months? B- what is the probability that the project will take longer than40 months? C- what is the probability that the project will take between 30 and 40 months? D- what is the probability the project will cost $5.1 million or less to complete? E- THe probability the project will cost between $5 and $6 million to complete ? GIve the netwrok diagram clearly.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

12th Edition

840062338, 840062346, 9780840062338, 978-0840062345

More Books

Students also viewed these General Management questions

Question

How does Method implement the marketing concept?

Answered: 1 week ago