The following CPM network has estimates of the normal time in weeks listed for the activities: A network diagram flowchart. The flows are as follows.

The following CPM network has estimates of the normal time in weeks listed for the activities:
A network diagram flowchart. The flows are as follows. A (7), B (2), D (5), F (4), and G (5). A (7), C (4), D (5), E (2), and G (5). A (7), B (2), D (5), E (2), and G (5).
a. Identify the critical path.
multiple choice 1
A-B-D-F-G
A-B-D-E-G
A-C-D-F-G
A-C-D-E-G
b. What is the length of time to complete the project?
c. Which activities have slack, and how much?
multiple choice 2
B,2 weeks; E,2 weeks.
D,1 week; E,2 weeks.
C,2 weeks; F,3 weeks.
C,1 week; E,2 weeks.
Here is a table of normal and crash times and costs.
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A 76 $ 7,000 $ 8,000
B 215,0007,000
C 439,00010,200
D 543,0004,500
E 212,0003,000
F 424,0007,000
G 545,0008,000
d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
multiple choice 3
B, C
A, E
B, D
A, C
d-2. What would be the total incremental cost?
d-3. Is the critical path changed?
multiple choice 4
Yes
No

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Richard L. Daft

12th edition

978-1118582695, 1118582691, 9781118801277, 111880127X, 978-1285861982

More Books

Students also viewed these General Management questions