The following data are average times per order over the last month for Groot Corp. days Move time 1 Inspection time 41 Queue time 3
The following data are average times per order over the last month for Groot Corp.
days | |
Move time | 1 |
Inspection time | 41 |
Queue time | 3 |
Wait time to start production | 2 |
Process time | 5 |
(Q): What is Manufacturing Cycle Efficiency (MCE)? Use two decimal places in the answer (for example, if the answer is 25%, key in "0.25").