The following data are given for Harry Company: Line Item Description Value Budgeted production 1 , 0 6 5 units Actual production 9 4 0

The following data are given for Harry Company:
Line Item Description Value
Budgeted production 1,065 units
Actual production 940 units
Materials:
Standard price per ounce $1.863
Standard ounces per completed unit 12
Actual ounces purchased and used in production 11,618
Actual price paid for materials $23,817
Labor:
Standard hourly labor rate $14.49 per hour
Standard hours allowed per completed unit 4.3
Actual labor hours worked 4,841
Actual total labor costs $78,666
Overhead:
Actual and budgeted fixed overhead $1,104,000
Standard variable overhead rate $28.00 per standard labor hour
Actual variable overhead costs $135,548
Overhead is applied on standard labor hours. (Round interim calculations to the nearest cent.)
The direct labor rate variance is
a. $20,097.42 unfavorable
b. $8,520.16 favorable
c. $20,097.42 favorable
d. $8,520.16 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Research Methods In Accounting

Authors: Malcolm Smith

5th Edition

1526490676, 978-1526490674

Students also viewed these Accounting questions