The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $1,678. A total of 30
The following data have been recorded for recently completed Job 450 on its job cost sheet. Direct materials cost was $1,678. A total of 30 direct labor-hours and 46 machine-hours were worked on the job. The direct labor wage rate is $12 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $18 per machine-hour. What is the total cost for Job 450?
a.) 2,770
b.) 2,590
c.) 1,754