Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following data is shown below: ActivityIDImmediate Predecessors Optimistic Time (o) Most Likely Time (m) Pessimistic Time (p) Start-----Plan detail expansion of pig pensA-123Acquire laborers
The following data is shown below:
ActivityIDImmediate Predecessors
Optimistic
Time (o)
Most Likely
Time (m)
Pessimistic
Time (p)
Start-----Plan detail expansion of pig pensA-123Acquire laborers to construct pig pensB-223Purchase construction materials for constructionCA444Erect two new water storage tanksDB234Implement pig pen construction worksED101320Monitor and control quality of construction activities.FE,D6812End construction activitiesGF123Document all project records and lessons learntHG234END-H---
Draw a project schedule network diagram to determine the critical path and project duration.
a.
Duration is 38 days and critical path is AEFGH
b.
Duration is 32 days and critical path is ACEFGH
c.
Duration is 37 days and critical path is ACDEFGH
d.
Duration is 35 days and critical path is ABCEFGH
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started