The following data is use for the questions 40 to 44 Project to excavate 100,000 cubic yards of dirt was estimated to take 5,000 hours
The following data is use for the questions 40 to 44 Project to excavate 100,000 cubic yards of dirt was estimated to take 5,000 hours of labor and cost $100,000 To date, 80,000 cubic yards of dirt has been excavated. To date, it has taken 4,250 hours and cost $ 78,000. It has been determined that the actual amount of excavation remaining is 25,000 cubic yards. What is the actual labor rate per hour of excavation to date