Question
The following data refers to four products A, B, C, D A B C D Price $75 $72 $45 $38 Raw materials $10 $5 $5
The following data refers to four products A, B, C, D
A | B | C | D | |
Price | $75 | $72 | $45 | $38 |
Raw materials | $10 | $5 | $5 | $10 |
Labor cost (fixed) | $20 | $20 | $20 | $20 |
The product that has the highest contribution margin is
Select one:
a.
product C
b.
product D
c.
product A
d.
product B
Question2
). Assume that a project manager expects to finish a project in 21 days as shown in the table below. However, the owner of the project wants it in 14 days and any period after 14 days the project manager has to pay penalty cost of $100 per day. Indirect project costs = $250 per day.
Project Activity and Cost Data
Activity | Normal Time (days) | Normal Cost ($) | Crash Time (days) | Crash Cost ($) | Immediate predecessor(s) |
A | 5 | 1000 | 4 | 1200 | - |
B | 5 | 800 | 3 | 2000 | - |
C | 2 | 600 | 1 | 900 | A, B |
D | 3 | 1500 | 2 | 2000 | B |
E | 5 | 900 | 3 | 1200 | C, D |
F | 2 | 1300 | 1 | 1400 | E |
G | 3 | 900 | 3 | 900 | E |
H | 5 | 500 | 3 | 900 | G |
Which activity will be crashed first?
Select one:
a.
activity E
b.
activity H
c.
activity D
d.
activity B
Question3
Assume that a project manager expects to finish a project in 21 days as shown in the table below. However, the owner of the project wants it in 14 days and any period after 14 days the project manager has to pay penalty cost of $100 per day. Indirect project costs = $250 per day.
Project Activity and Cost Data
Activity | Normal Time (days) | Normal Cost ($) | Crash Time (days) | Crash Cost ($) | Immediate predecessor(s) |
A | 5 | 1000 | 4 | 1200 | - |
B | 5 | 800 | 3 | 2000 | - |
C | 2 | 600 | 1 | 900 | A, B |
D | 3 | 1500 | 2 | 2000 | B |
E | 5 | 900 | 3 | 1200 | C, D |
F | 2 | 1300 | 1 | 1400 | E |
G | 3 | 900 | 3 | 900 | E |
H | 5 | 500 | 3 | 900 | G |
How much is the per week cost of crashing of activity H?
Select one:
a.
$900
b.
$500
c.
$400
d.
$200
Question4
Assume the following Hamburger sandwich processes
Order 20 second
Bread 10 seconds
Fill 40 seconds
Toaster 30 seconds
Wrap 5 seconds.
In the above example, the throughput time is:
a.
105 seconds
b.
60 seconds
c.
100 seconds
d.
40 seconds
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started