The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.97; actual, $2.03 Standard yards per unit: standard, 4.74 yards;
-
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.97; actual, $2.03 Standard yards per unit: standard, 4.74 yards; actual, 5.10 yards Units of production: 9,100 Calculate the direct materials quantity variance.
a.$6,650.28 unfavorable
b.$6,650.28 favorable
c.$6,453.72 favorable
d.$6,453.72 unfavorable