The following data relates to QA firm. Cost standards: Direct material 3 kg @ $2.50 per kg $7.50 Direct labour 5 hours @ $7.50 per
The following data relates to QA firm. Cost standards:
|
|
|
|
Direct material | 3 kg @ $2.50 per kg |
| $7.50 |
Direct labour | 5 hours @ $7.50 per hour |
| $37.50 |
Actual results:
7,800 units were produced.
|
|
|
|
Direct material purchased | 25,000 kg @ $2.60 |
| $65,000 |
Direct material used | 23,100 kg |
|
|
Direct labour | 40,100 hours @ $7.30 |
| $292,730 |
Calculate the direct material quantity variance.A.
$780 (F)
B.
$750 (U)
C.
$800 (F)
D.
$750 (F)
Clear my choice
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started