The following data were drawn from the records of Gibson Corporation. Planned volume for year (static budget) 3,200 units Standard direct materials cost per unit

The following data were drawn from the records of Gibson Corporation.

Planned volume for year (static budget) 3,200 units
Standard direct materials cost per unit 3.00 pounds @ $ 1.50 per pound
Standard direct labor cost per unit 3.80 hours @ $ 3.40 per hour
Total expected fixed overhead costs $ 13,760
Actual volume for the year (flexible budget) 3,500 units
Actual direct materials cost per unit 2.40 pounds @ $ 1.90 per pound
Actual direct labor cost per unit 4.00 hours @ $ 2.90 per hour
Total actual fixed overhead costs $ 9,360

Required

Prepare a materials variance information table showing the standard price, the actual price, the standard quantity, and the actual quantity.

Calculate the materials price and usage variances. Indicate whether the variances are favorable (F) or unfavorable (U).

Prepare a labor variance information table showing the standard price, the actual price, the standard hours, and the actual hours.

Calculate the labor price and usage variances. Indicate whether the variances are favorable (F) or unfavorable (U).

Calculate the predetermined overhead rate, assuming that Gibson uses the number of units as the allocation base.

Calculate the fixed cost spending variance. Indicate whether the variance is favorable (F) or unfavorable (U).

Calculate the fixed cost volume variance. Indicate whether the variance is favorable (F) or unfavorable (U).

Complete this question by entering your answers in the tabs below.

Req A

Req B

Req C

Req D

Req E to G

Prepare a materials variance information table showing the standard price, the actual price, the standard quantity, and the actual quantity. (Round "Standard price" and "Actual price" to 2 decimal places.)

Materials Variance Information Table
Standard price

per pound

Actual price

per pound

Standard quantity for flexible budget pounds
Actual quantity used pounds

Complete this question by entering your answers in the tabs below.

Req A

Req B

Req C

Req D

Req E to G

Calculate the materials price and usage variances. Indicate whether the variances are favorable (F) or unfavorable (U).(Select "None" if there is no effect (i.e., zero variance).)

Material price variance
Material usage variance

Complete this question by entering your answers in the tabs below.

Req A

Req B

Req C

Req D

Req E to G

Prepare a labor variance information table showing the standard price, the actual price, the standard hours, and the actual hours. (Round "Standard price" and "Actual price" to 2 decimal places.)

Labor Variance Information Table
Standard price per hour
Actual price per hour
Standard hours for flexible budget
Actual hours used

Complete this question by entering your answers in the tabs below.

Req A

Req B

Req C

Req D

Req E to G

Calculate the labor price and usage variances. Indicate whether the variances are favorable (F) or unfavorable (U). (Select "None" if there is no effect (i.e., zero variance).)

Labor price variance
Labor usage variance

Complete this question by entering your answers in the tabs below.

Req A

Req B

Req C

Req D

Req E to G

Calculate the predetermined overhead rate, assuming that Gibson uses the number of units as the allocation base. Calculate the fixed cost spending variance and the fixed cost volume variance. Indicate whether the variance is favorable (F) or unfavorable (U). (Round "Predetermined overhead rate" answer to 2 decimal places. Select "None" if there is no effect (i.e., zero variance).)

Show less

e. Predetermined overhead rate per unit
f. Fixed cost spending variance
g. Fixed cost volume variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Speed Of Risk Lessons Learned On The Audit Trail

Authors: Richard F. Chambers, CIA, QIAL, CGAP, CCSA, CRMA

2nd Edition

163454059X, 978-1634540599

More Books

Students also viewed these Accounting questions

Question

explain the concept of strategy formulation

Answered: 1 week ago