The following details were extracted from the standard cost card of a component: Raw materials: 2 Kgs @ $4 per Kg Direct labour: 5 hrs
The following details were extracted from the standard cost card of a component:
Raw materials: 2 Kgs @ $4 per Kg
Direct labour: 5 hrs @ $5.50 per hour
During the period, actual results were as follows:
Production- 1,900 components.
Direct material purchase and usage- 4,000 Kgs at a cost of $18,000.
Wage Paid: (10,100 hrs) $61,000
What is the Material Price Variance?
Select one:
A.1,000 (Favourable)
B. 2,000 (Adverse)
C. 0 (Neither Favourable or Adverse)
D. 4,000 (Adverse)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started