The following direct materials and direct labor data pertain to the operations of Pharoah Company for the month of August. Costs Actual labor rate $

The following direct materials and direct labor data pertain to the operations of Pharoah Company for the month of August.

Costs

Actual labor rate $ 13 per hour
Actual materials price $ 110 per ton
Standard labor rate $ 12.50 per hour
Standard materials price $ 111 per ton

Quantities

Actual hours incurred and used 4,500 hours
Actual quantity of materials purchased and used 1,600 tons
Standard hours used 4,580 hours
Standard quantity of materials used 1,575 tons

(a) Compute the total, price, and quantity variances for materials and labor.

Total materials variance
Materials price variance
Materials quantity variance
Total labor variance
Labor price variance
Labor quantity variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Quality Auditing

Authors: Denis Pronovost

1st Edition

0873894766, 9780873894760

More Books

Students also viewed these Accounting questions

Question

What do you mean by dual mode operation?

Answered: 1 week ago

Question

Explain the difference between `==` and `===` in JavaScript.

Answered: 1 week ago

Question

Discuss consumer-driven health plans.

Answered: 1 week ago