The following eight activities constitute an overall bar chart portrayal of a four-month project: After 2 months, activity A and D are complete with B
The following eight activities constitute an overall bar chart portrayal of a four-month project:
After 2 months, activity A and D are complete with B 80% complete, C 75% complete and E 25% complete. The actual cost for the tasks by then is $18,500. Using the earned value analysis, determine the project performance and estimated cost at completion.