The following exercise involves the information in the figure shown below on constructing a home. Task Length Dependency a . Write and agree on contracts

The following exercise involves the information in the figure shown below on constructing a home.
Task Length Dependency
a. Write and agree on contracts 4 weeks
b. Secure financing 4 weeks a
c. Obtain permits 5 weeks a, b
d. Site work 4 weeks a, b, c
e. Build foundation 3 weeks b, c, d
f. Erect walls 3 weeks d, e
g. Build roof 4 weeks f
h. Rough in plumbing 2 weeks f
i. Rough in electrical 2 weeks f
j. Rough in furnace and air conditioning 1 week f
k. Finish exterior 5 weeks f, g, i
l. Finish interior 6 weeks f, g, h, i, j
m. Finish plumbing 2 weeks h, i
n. Finish electrical 1 week i, l
o. Finish furnace and air conditioning 1 day j, l
p. Wait for inspection 2 weeks k, l, m, n, o
What is the completion time?
Incorrect: Your answer is incorrect.
wk

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions