The following four months of data were collected on utility cost and the number of labor hours in a factory. Month Utility cost Labor hours
The following four months of data were collected on utility cost and the number of labor hours in a factory.
Month
Utility cost
Labor hours
January $115,550 7,540
February 106,782 6,900
March 105,400 6,840
April 110,112 7,150
Using the high-low method, compute the variable rate for the utility cost. Note. Enter numbers only-- do not use a dollar sign ($) or comma.