The following information applies to the questions displayed below.] Consider the following table of activities for a minor project on a construction site. Activity Earliest
The following information applies to the questions displayed below.] Consider the following table of activities for a minor project on a construction site. Activity Earliest Start Time (EST) Expected Durations (days) Earliest Completion Time (ECT) A1 0 5 5 A2 ECT(A1) = 5 2 7 A3 ECT(A2) = 7 6 13 A4 ECT(A2) 4 What is the earliest start time (EST) for activity 4 (A4)