[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa

[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023
Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400
Estimated costs to complete as of year-end 5,041,000 2,414,000 0
Billings during the year 2,190,000 2,496,000 5,314,000
Cash collections during the year 1,895,000 2,400,000 5,705,000

Westgate recognizes revenue over time according to percentage of completion.

Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

Please help to solve this problem. Correct answer only. Thank you!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Tools for Business Decision Making

Authors: Paul D. Kimmel, Jerry J. Weygandt, Donald E. Kieso

9th edition

1-119-49356-3, 1119493633, 1119493560, 978-1119493631

More Books

Students also viewed these Accounting questions