[The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa

[The following information applies to the questions displayed below.]

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:

2021 2022 2023

Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400

Estimated costs to of year-end 5,396,000 2,204,000 0

Billings during the year 2,140,000 3,256,000 4,604,000

Cash collections during the year 1,870,000 3,200,000 4,930,000

Westgate recognizes revenue over time according to percentage of completion.

Required:

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

2021 2022 2023

Revenue

Gross profit (loss)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Multicolumn Journal

Authors: Claudia Gilbertson

11th Edition

1337565423, 9781337565424

More Books

Students also viewed these Accounting questions

Question

The relevance of the information to the interpreter

Answered: 1 week ago