Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

[The following information applies to the questions displayed below.] The Gilster Company, a machine tooling firm, has several plants. One plant, located in St. Cloud,

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed [The following information applies to the questions displayed below.] The Gilster Company, a machine tooling firm, has several plants. One plant, located in St. Cloud, Minnesota, uses a job order costing system for its batch production processes. The St. Cloud plant has two departments through which most jobs pass. Plant-wide overhead, which includes the plant manager's salary, accounting personnel, cafeteria, and human resources, is budgeted at $250,000. During the past year, actual plantwide overhead was $242,000. Each department's overhead consists primarily of depreciation and other machine-related expenses. Selected budgeted and actual data from the St. Cloud plant for the past year are as follows. Budgeted department overhead (excludes plantwide overhead) Actual department overhead Expected total activity: Direct labor hours Machine-hours Actual activity:. Direct labor hours. Machine-hours Department Department B $ 97,500 120,000 $540,600 558,600 56,000 15,000 13,000 53,000 58,500 14,000 13,700 55,000 For the coming year, the accountants at the St. Cloud plant are in the process of helping the sales force create bids for several jobs. Projected data pertaining only to job no. 110 are as follows. Direct materials $21,500 Direct labor cost: Department A (2,400 hr) 36,000 Department B (800 hr) 11,600 Machine-hours projected: Department A 100 Department B Units produced 1,200 12,000 Required: a-1. Assume the St. Cloud plant uses a single plantwide overhead rate to assign all overhead (plantwide and department) costs to jobs. Use expected total direct labor hours to compute the overhead rate. a-2. What is the expected cost per unit produced for job no. 110? Answer is complete and correct. Complete this question by entering your answers in the tabs below. Req A Req A2 Assume the St. Cloud plant uses a single plantwide overhead rate to assign all overhead (plantwide and department) costs to jobs. Use expected total direct labor hours to compute the overhead rate. (Round your answer to 2 decimal places.) Overhead rate $ 12.51 per direct labor hour Red AT Req A2 > Assume the St. Cloud plant uses three separate overhead rates to assign overhead costs to jobs. b-1. Find the plant wide overhead rate by using expected machine hours. b-2. Find the department overhead rate using expected machine hours for Department A and Department B. b-3. Calculate the projected manufacturing costs per unit for job 110 using the three separate rates computed in b-1 and b-2. Complete this question by entering your answers in the tabs below. Req B1 Req B2 Req B3 . Find the plant wide overhead rate by using expected machine hours. (Round your answer to 2 decimal places.) Plantwide overhead rate $ 3.79 per machine hour Rog Br. Req B2 > c-1. The sales policy at the St. Cloud plant dictates that job bids be calculated by adding 23 percent to total manufacturing costs. What would be the bid for job no. 110 using the overhead rate from part a? c-2. The sales policy at the St. Cloud plant dictates that job bids be calculated by adding 23 percent to total manufacturing costs. What would be the bid for job no. 110 using the overhead rate from part b? c-3. Which of the overhead allocation methods would you recommend? Complete this question by entering your answers in the tabs below. Req C1 Req C2 Req C3 The sales policy at the St. Cloud plant dictates that job bids be calculated by adding 23 percent to total manufacturing costs. What would be the bid for job no. 110 using the overhead rate from part a? (Round your intermediate calculations to 2 decimal places and final answer to the nearest whole dollar amount.) $ Bid price 13,944,756 ReqC1 Req C2 > d. Compute the under- or overapplied overhead for the St. Cloud plant for the year. (Round your intermediate calculations to 2 decimal places.) Answer is complete but not entirely correct. Overapplied i $ 8,000 e. A St. Cloud subcontractor has offered to produce the parts for job no. 110 for a price of $8 per unit. Assume the St. Cloud sales force has already committed to the bid price based on the calculations in part b. Should the St. Cloud plant buy the $8 per unit part from the subcontractor or continue to make the parts for job no. 110 itself? Buy part from the subcontractor Continue to make the part f. Would your response to part e change if the St. Cloud plant could use the facilities necessary to produce parts for job no. 110 for another job that could earn an incremental profit of $23,000? Incremental profit earned by producing the other job Incremental cost of buying the parts from the subcontractor Increase in total profits

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information System

Authors: James A. Hall

7th Edition

978-1439078570, 1439078572

Students also viewed these Accounting questions

Question

Please make it fast 6 5 1 .

Answered: 1 week ago

Question

_____ choice of whether to purchase parts or to produce them

Answered: 1 week ago