The following information concerns progress at day 40 of an Internet marketing project. A. In your explanation include the Critical Ratio, CV, SV, CPI, SPI,

The following information concerns progress at day 40 of an Internet marketing project. A. In your explanation include the Critical Ratio, CV, SV, CPI, SPI, ETC and EAC. B. Determine if the project is in control based on the time and cost to date. If not, what is the cost overage or underage. C. Please draw the project as a Gannt Chart and as a Pert Chart. What is the critical path of the project? D. Explain how activity D could have no duration, and no budget.

Activity Predecessors Duration Budget Actual Cost % Complete
A - 10 300 250 100
B A 8 400 450 100
C A 12 350 380 100
D C 0 0 0 -
E B,D 18 405 400 70
F E 16 450 - 0

Explain, in detail, what ETC and EAC is telling us? A. How is it different from BAC or the total of the Actual Cost to date + the remainder of Budgeted work to be done? B. What exactly is the formula telling us? C. Why do I want to know this?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of Responsible Management Global Sustainability Responsibility and Ethics

Authors: Oliver Laasch

1st Edition

9781285981321, 1285080262, 1285981324, 978-1285080260

More Books

Students also viewed these General Management questions

Question

Compare and contrast eager with lazy replication.

Answered: 1 week ago