Question

1 Approved Answer

The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials

The following information is available for Department Z for the month of July:

Units Cost
Work in process, July 1 (70% complete) 2,000
Direct materials $ 6,000
Direct labor 3,000
Manufacturing overhead 4,000
Total work in process, July 1 $13,000
Started in production during July 20,000
Costs added:
Direct materials $18,000
Direct labor 8,000
Manufacturing overhead 10,000
Total costs added during July $36,000
Work in process, July 31, (80% complete) 2,000

Materials are added at the beginning of the process. Department Z's cost of goods transferred out using the FIFO method would bemethod would be

a.$40,250.

b.$44,500.

c.$45,540.

d.$45,775

Materials are added at the beginning of the process. Department Z's cost per equivalent unit of production for conversion costs using the FIFO method would be

a.$0.73.

b.$1.18.

c.$1.02.

d.$0.85.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Energy Audits A Workbook For Energy Management In Buildings

Authors: Tarik Al-Shemmeri

1st Edition

0470656085, 978-0470656082

More Books

Students also viewed these Accounting questions

Question

understand the meaning of the terms discipline and grievance

Answered: 1 week ago