Question
The following information is for the third quarter of this year: Planned Actual Production 80,000 units 81,000 units Direct Material Purchases 225,000 lbs. @ $
The following information is for the third quarter of this year:
Planned Actual
Production 80,000 units 81,000 units
Direct Material Purchases 225,000 lbs. @ $ 3.00 225,000 lbs. @ $ 2.90
Direct Material Used 200,000 lbs. @ $ 3.00 200,500 lbs. @ $ 2.90
Direct labor 160,000 hrs. @ $ 10.00 140,000 hrs. @ $ 12.00
Variable manufacturing overhead $ 200,000 $ 202,000
Fixed manufacturing overhead $ 721,000 $ 723,500
Standard direct material pounds per unit 2.5
Standard direct labor hour per unit 2.0
Variable Overhead Rate per direct labor hour $
Required: Calculate the following three overhead variances; overhead is allocated based on direct labor hours.
- Material Purchase Variance
- Material Quantity Variance
- Direct Labor Rate Variance
- Direct Labor Quantity Variance
- Overhead volume variance
- Overhead efficiency variance
- Overhead spending variance
- Formulate a hypothesis about the cause of these variances
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started