The following information is for X Company: Budgeted proudction 10,200 units Actual production 11,300 units Budgeted costs: Total fixed $208,300 Per-unit variable $9.01 Actual costs:
The following information is for X Company:
Budgeted proudction | 10,200 units | |
Actual production | 11,300 units | |
Budgeted costs: | ||
Total fixed | $208,300 | |
Per-unit variable | $9.01 | |
Actual costs: | ||
Total fixed | $204,780 | |
Total variable | $136,668 |
What was the flexible budget variance (a positive number means a favorable variance and a negative number means an unfavorable variance)?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started