Answered step by step
Verified Expert Solution
Question
1 Approved Answer
The following information relates to Lancashire Manufacturing: To produce a unit of product: Mixing department 3 minutes per unit Molding department 5 minutes per unit
The following information relates to Lancashire Manufacturing: To produce a unit of product:
Mixing department | 3 minutes per unit |
Molding department | 5 minutes per unit |
Casting department | 7 minutes per unit |
Finishing department | 4 minutes per unit |
There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes. How long does it take to produce a batch of 20 units under a traditional manufacturing approach?
a.380 minutes
b.415 minutes
c.35 minutes
d.None of these choices are correct.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started