The following information relates to Lancashire Manufacturing: To produce a unit of product: Mixing department 3 minutes per unit Molding department 5 minutes per unit

The following information relates to Lancashire Manufacturing: To produce a unit of product:

Mixing department 3 minutes per unit
Molding department 5 minutes per unit
Casting department 7 minutes per unit
Finishing department 4 minutes per unit

There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes. How long does it take to produce a batch of 20 units under a traditional manufacturing approach?

a.380 minutes

b.415 minutes

c.35 minutes

d.None of these choices are correct.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

politeness and modesty, as well as indirectness;

Answered: 1 week ago