Question
The following information relates to Lancashire Manufacturing: To produce a unit of product: Mixing department 3 minutes per unit Molding department 5 minutes per unit
The following information relates to Lancashire Manufacturing: To produce a unit of product:
Mixing department | 3 minutes per unit |
Molding department | 5 minutes per unit |
Casting department | 7 minutes per unit |
Finishing department | 4 minutes per unit |
There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes. What is the production rate?
a.19.0 units per hour
b.7.0 units per hour
c.8.6 units per hour
d.21.0 units per hour
The following information relates to Cranmore Manufacturing: To produce a unit of product:
Cutting department | 5 minutes per unit |
Welding department | 8 minutes per unit |
Polishing department | 3 minutes per unit |
Finishing department | 4 minutes per unit |
There is a wait time of 5 minutes before the cutting department begins a batch, 15 minutes between the cutting and welding departments, a move and pre-wait between welding and polishing of 12 minutes, and a move and pre-wait between the polishing and finishing departments of 8 minutes. What is the production rate?
a.20.0 units per hour
b.15.0 units per hour
c.7.5 units per hour
d.12.0 units per hour
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started