Question
The following information was obtained from KMG Manufacturing Company. Standard Data: Direct material4 yards @ $4 per yard Direct labour3 hours @ $6 per hour
The following information was obtained from KMG Manufacturing Company.
Standard Data:
Direct material4 yards @ $4 per yard
Direct labour3 hours @ $6 per hour
Variable manufacturing overheads $2 per hour
Actual Data:
Direct material48,000 yards @ $4.20 per yard
Direct labour34,000 hours @ $5.20 per hour
Variable manufacturing overhead34,000 hours totalling $80,000
Actual units produced18,000
Required:
a)Compute the direct material price variance(3 marks)
b)Calculate the direct material usage variance(3 marks)
c)Total Direct Material Cost variance(3 marks)
d)Calculate direct labour rate variance(3 marks)
e)Calculate direct labour efficiency variance(3 marks)
f)Total Direct Labour Costvariance(3 marks)
g)Variable Manufacturing Overhead Rate(3 marks)
h)Variable Manufacturing Overhead Efficiency(3 marks)
i)Give One (1) possible cause of an adverse material price variance.(1 mark)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started