Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The following information was obtained from KMG Manufacturing Company. Standard Data: Direct material 4 yards @ $4 per yard Direct labour 3 hours @ $6

The following information was obtained from KMG Manufacturing Company.

Standard Data:

Direct material 4 yards @ $4 per yard

Direct labour 3 hours @ $6 per hour

Variable manufacturing overheads $2 per hour

Actual Data:

Direct material 48,000 yards @ $4.20 per yard

Direct labour 34,000 hours @ $5.20 per hour

Variable manufacturing overhead 34,000 hours totalling $80,000

Actual units produced 18,000

Required:

  1. Compute the direct material price variance
  2. Calculate the direct material usage variance
  3. Total Direct Material Cost variance
  4. Calculate direct labour rate variance
  5. Calculate direct labour efficiency variance
  6. Total Direct Labour Cost variance
  7. Variable Manufacturing Overhead Rate
  8. Variable Manufacturing Overhead Efficiency
  9. Give One (1) possible cause of an adverse material price variance.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective Auditing For Corporates Ensuring That All The Risks Are Covered

Authors: Bloomsbury, Joe Oringel

1st Edition

1849300445, 978-1849300445

More Books

Students also viewed these Accounting questions