The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede. Activity Duration
The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede.
Activity | Duration (weeks) | Precedes |
---|---|---|
A (start) | 3 | B, C |
B | 7 | F |
C | 2 | E |
E | 4 | F |
F (end) | 4 |
weeks.
Determine the
slack time
for each of the activities.
(Enter
your responses as whole
numbers.)