Question
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede:
This exercise contains only parts b, c, and d.
Part 2 b) The activities on the critical path are ________ .
Part 3 c) The total project completion time for Rafay Ishfaq's software firm is ________weeks. (Enter your response as a whole number.)
Part 4 d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.)
Activity Slack Time (weeks)
A
B
C
D
E
F
What is the total slack for the non critical path(s) in the project? ________week(s) (Enter your response as a whole number.)
\begin{tabular}{ccc} \hline Activity & Duration (weeks) & Precedes \\ \hline A (start) & 2 & B,C \\ B & 3 & E \\ C & 6 & F \\ E & 2 & F \\ F (end) & 3 & - \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3