Question
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company:
Activity Center | Variable | Fixed | Cost Driver |
Statement inquiry | $82,790 | $162,000 | 3,400 labor hours |
Correspondence | $9,996 | $26,000 | 2,800 letters |
Account billing | $120,000 | $80,000 | 2,400,000 lines |
Payment verification | $12,470 | $76,000 | 21,500 accounts |
In September, actual total costs and activity were as follows:
Activity Center | Total Costs | Driver Amount |
Statement inquiry | $241,302 | 3,240 labor hours |
Correspondence | $35,591 | 2,660 letters |
Account billing | $200,398 | 2,390,000 lines |
Payment verification | $88,244 | 21,540 accounts |
Required Compute the flexible-budget variances for the following two activity cost items (round unit costs to two decimal places and enter favorable variances as positive numbers and unfavorable variances as negative numbers):
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started