The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company: Activity Center
The following is total monthly budgeted cost and activity information for the four activity centers in the billing department of Oregon Power Company:
Activity Center | Variable | Fixed | Cost Driver |
Account inquiry | $80,172 | $153,000 | 3,400 labor hours |
Correspondence | $9,772 | $26,000 | 2,800 letters |
Account billing | $175,000 | $83,000 | 2,500,000 lines |
Bill verification | $10,260 | $79,000 | 18,000 accounts |
In September, actual costs and activity were as follows:
Activity Center | Total Costs | Driver Amount |
Account inquiry | $234,071 | 3,410 labor hours |
Correspondence | $36,044 | 2,610 letters |
Account billing | $271,699 | 2,700,000 lines |
Bill verification | $88,833 | 18,010 accounts |
Required Compute the flexible-budget variances for the following two activity cost items (round all answers to the nearest dollar and enter favorable variances as positive numbers and unfavorable variances as negative numbers): #1 Account inquiry #2 Account billing
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started