The following list represents CPM network of a project. Activity Normal time ( day ) Crash time ( days ) Normal cost Crash cost Predecessor

The following list represents CPM network of a project.
Activity Normal time (day) Crash time (days)
Normal cost
Crash cost Predecessor
A 86 $1,000 $1,600---
B 107 $2,000 $2,600---
C 54 $500 $1,000 A
D 97 $4,000 $4,200 A, B
E 21 $3,000 $4,000 C, D
Suppose that the project manager is willing to spend any amount of cost to complete the project as fast as possible. What will be the project duration after the crashing (i.e., crashing to the maximum extent without concerning the crashing cost)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Retailing Management

Authors: Michael Levy, Barton A Weitz

8th Edition

0073530026, 9780073530024

More Books

Students also viewed these General Management questions