The following partial job cost sheet is for a job lot of 2,600 units completed. Customer's Name Huddits Company Date March 8 March 11 Direct
The following partial job cost sheet is for a job lot of 2,600 units completed. Customer's Name Huddits Company Date March 8 March 11 Direct Materials Cost Requisition #55 # 56 $ 44,650 34,500 JOB COST SHEET 1. What is the total cost of this job lot? 2. What is the total cost per unit completed? Direct Labor Quantity 2,600 Time Ticket Cost #1 to #10 $ 60,900 Job Number 202 Overhead Rate Date March 8 150% of Direct Labor Cost Cost $ 91,350