The following partially completed process cost summary describes the July production activities of the Molding department at Ashad Company. Its production output is sent to the next department. All direct materials are added to products when processing begins. Beginning work in process inventory is 20% complete with respect to conversion. Equivalent Units of Production Units transferred out Units of ending work in process Equivalent units of production Direct Materials 37,000 EUP 4,500 EUP 41,500 EUP Conversion 37,000 EUP 2,700 EUP 39,700 EUP Costs per EUP Costs of beginning work in process Costs incurred this period Total costs Direct Materials $ 41,850 431,250 $ 473,100 Conversion $ 4,880 237,290 $ 242,170 Units in beginning work in process (all completed during July) Units started this period Units completed and transferred out Units in ending work in process 4,000 37,500 37,000 4,500 Prepare its process cost summary using the weighted average method. (Round "Cost per EUP" to 2 decimal places.) Costs Charged to Production $ 0.00 Total costs to account for Total costs accounted for "Difference due to rounding cost/unit $ 0.00 Unit Reconciliation Units to account for Total units to account for Total units accounted for Total units accounted for Equivalent Units of Production (EUP)-Weighted Average Method Units % Materials EUP-Materials % Conversion EUP. Conversion Equivalent units of production Cost per EUP Materials Conversion Costs EUP Costs EUP 0 0 Cost per Total cost EUP EUP Total costs Equivalent units of production Cost per equivalent unit of production Cost Assignment and Reconciliation Costs transferred out Direct materials Conversion Total transferred out Costs of ending work in process Total cost EUP Cost per EUP $ 0.00 al Equivalent Units of Production (EUP)-Weighted Average Method Units % Materials EUP-Materials % Conversion EUP. Conversion Equivalent units of production Cost per EUP Materials Conversion Costs Costs EUP EUP 0 Total costs + Equivalent units of production Cost per equivalent unit of production Cost Assignment and Reconciliation Costs transferred out Direct materials Conversion Total transferred out Cost per EUP Total cost EUP Cost per EUP Total cost $ EUP 0.00 0.00 $ Costs of ending work in process Direct materials Conversion Total ending work in process Total costs accounted for