Question
The following particulars relate to a contract undertaken by Ajit Engineers: Rs Materials sent to site 85,349 Labour engaged on site 74,375 Plant installed at
The following particulars relate to a contract undertaken by Ajit Engineers:
Rs | |
Materials sent to site | 85,349 |
Labour engaged on site | 74,375 |
Plant installed at site | 15,000 |
Direct expenditure | 3,167 |
Establishment charges | 4,126 |
Materials returned to stores | 549 |
Work certified | 1,95,000 |
Cost of work not certified | 4,500 |
Materials in hand at the end of year | 1,883 |
Wages accrued at the end of year | 2,400 |
Direct expenses accrued at the end of year | 240 |
Value of plant at the end of year | 11,000 |
The contract price agreed | 2,50,000 |
Cash received from contract | 1,80,000 |
You are required to prepare the contract account showing profit, contractee's account and show suitable entries in the balance sheet of the contractor.
Please do not copy from Chegg. Otherwise i have to report the answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started