Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The following personnel have been assigned full-time to the Red Zuma project team: 4 marketing specialists 4 design engineers 4 development engineers 4 industrial engineers

image text in transcribed
image text in transcribed
image text in transcribed
The following personnel have been assigned full-time to the Red Zuma project team: 4 marketing specialists 4 design engineers 4 development engineers 4 industrial engineers 4 test riders 2 purchasing agents Use the file from Part 1 and the information contained in Tables A2.6 and A2.7 to assign resources to the project schedule. TABLE A2.6 Red Zuma Project Resources TABLE A27 Red Zuma Resource Assignments Top management is not happy with the resource-constrained schedule. Robin Lane, the president, has promised retailers that ARC will begin production in time for the major trade show in Las Vegas on January 22, 2016, which means the project needs to be completed by January 17, 2016. She has authorized working the first available Saturday of each month to help the project get completed sooner. She realizes that this will only reduce the project duration by 1213 days. After talking to the engineers, everyone agrees that they do not have to wait for the Detailed Product Design to be 100% completed before starting to build the prototype. The consensus is that Building the Prototype can start 30 days after the start of the Detailed Product Design. Likewise the Final Manufacturing Process can start 15 days after the start of Finalized Product Design. Dewey Martin, director of product development, is also willing to add personnel to the project. He is willing to make available at least one more Development, Design, and/or Industrial Engineer to the project as well as Marketing Specialist. Since there is an acute shortage of personnel at ARC he requests that you only use additional manpower that will help meet the deadline. Your objective is to develop a schedule that will satisfy the deadline with minimum additional resource usage. Prepare a memo that addresses the following questions: 1. What was the impact of introducing Startto-Start lags to the schedule and budget? 2. Which, if any additional personnel assignments, would you choose to complete the project before the January 17 th deadline? Explain your choices as well as the reasons for not choosing other options. 3. How have these changes affected the sensitivity of the network and the critical path? Include a Gantt chart with a schedule table displaying free and total slack for the new schedule. Note: Do not assign new personnel to specific tasks, simply add them to the Resouree Sheet. All new personnel are available full time (100%) The following personnel have been assigned full-time to the Red Zuma project team: 4 marketing specialists 4 design engineers 4 development engineers 4 industrial engineers 4 test riders 2 purchasing agents Use the file from Part 1 and the information contained in Tables A2.6 and A2.7 to assign resources to the project schedule. TABLE A2.6 Red Zuma Project Resources TABLE A27 Red Zuma Resource Assignments Top management is not happy with the resource-constrained schedule. Robin Lane, the president, has promised retailers that ARC will begin production in time for the major trade show in Las Vegas on January 22, 2016, which means the project needs to be completed by January 17, 2016. She has authorized working the first available Saturday of each month to help the project get completed sooner. She realizes that this will only reduce the project duration by 1213 days. After talking to the engineers, everyone agrees that they do not have to wait for the Detailed Product Design to be 100% completed before starting to build the prototype. The consensus is that Building the Prototype can start 30 days after the start of the Detailed Product Design. Likewise the Final Manufacturing Process can start 15 days after the start of Finalized Product Design. Dewey Martin, director of product development, is also willing to add personnel to the project. He is willing to make available at least one more Development, Design, and/or Industrial Engineer to the project as well as Marketing Specialist. Since there is an acute shortage of personnel at ARC he requests that you only use additional manpower that will help meet the deadline. Your objective is to develop a schedule that will satisfy the deadline with minimum additional resource usage. Prepare a memo that addresses the following questions: 1. What was the impact of introducing Startto-Start lags to the schedule and budget? 2. Which, if any additional personnel assignments, would you choose to complete the project before the January 17 th deadline? Explain your choices as well as the reasons for not choosing other options. 3. How have these changes affected the sensitivity of the network and the critical path? Include a Gantt chart with a schedule table displaying free and total slack for the new schedule. Note: Do not assign new personnel to specific tasks, simply add them to the Resouree Sheet. All new personnel are available full time (100%)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Financial Reporting And Analysis A Global Perspective

Authors: S. David Young, Jacob Cohen, Daniel A. Bens

4th Edition

1119494575, 978-1119494577

More Books

Students also viewed these Accounting questions

Question

What five theories explain our need for sleep?

Answered: 1 week ago

Question

Write a note on job design.

Answered: 1 week ago

Question

Compute the derivative of f(x)cos(-4/5x)

Answered: 1 week ago

Question

Discuss the process involved in selection.

Answered: 1 week ago

Question

Differentiate tan(7x+9x-2.5)

Answered: 1 week ago

Question

What roles have these individuals played in your life?

Answered: 1 week ago