The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI and SPI. Then
The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.
Activity | Predecessor | Duration (wks) | Budget ($) | Actual Cost ($) | %Complete |
a | - | 2 | 600 | 400 | 100 |
b | - | 3 | 150 | 180 | 100 |
c | a | 2 | 250 | 300 | 100 |
d | a | 5 | 500 | 400 | 20 |
e | b, c | 4 | 400 | 200 | 20 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started