Question

1 Approved Answer

The following project is at the end of its 6 th week. Find the cost and schedule variances. Also find the CPI and SPI. Then

The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods.

Activity Predecessor Duration (wks) Budget ($) Actual Cost ($) %Complete
a - 2 600 400 100
b - 3 150 180 100
c a 2 250 300 100
d a 5 500 400 20
e b, c 4 400 200 20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: John Pearce , Richard Robinson

13th Edition

0078029295, 978-0078029295

More Books

Students also viewed these General Management questions

Question

LO12.3 Explain how demand is seen by a pure monopoly.

Answered: 1 week ago