The following represent activities in Marc Massoud's Construction Company project. ACTIVITY IMMEDIATE PREDECESSOR(S) TIME(weeks) A 1 B 4 C A 1 D B 5 E
The following represent activities in Marc Massoud's Construction Company project. ACTIVITY IMMEDIATE PREDECESSOR(S) TIME(weeks) A 1 B 4 C A 1 D B 5 E B 2 F C, E 7 G D 2 H F, G 3