The following represents a project that should be scheduled using G . table [ [ , , TIMES ( DAYS ) ] , [

The following represents a project that should be scheduled using G.
\table[[,,TIMES (DAYS)],[,IMMEDIATE,,,],[ACTIVITY PREDECESSORS,a,m,b,],[A,-,1,2,6],[B,-,1,2,7],[C,A,2,2,11],[D,A,1,8,9],[E,B,1,2,3],[F,C, D,3,4,11],[G,D, E,1,3,11],[H,F, G,2,3,11]]
b. What is the critical path?
A-C-F-H
A-D-F-H
A-D-G-H
B-E-G-H
c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)
Project completion time days
d. What is the probability of completing this project within 19 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations and Supply Chain Management

Authors: Cecil B. Bozarth, Robert B. Handfield

3rd edition

132747324, 978-0132747325

More Books

Students also viewed these General Management questions