Question
The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 4 7 B 2
The following represents a project that should be scheduled using CPM:
ACTIVITY | IMMEDIATE PREDECESSORS | TIMES (DAYS) | ||
---|---|---|---|---|
a | m | b | ||
A | 1 | 4 | 7 | |
B | 2 | 3 | 7 | |
C | A | 3 | 5 | 7 |
D | A | 5 | 6 | 10 |
E | B | 1 | 2 | 6 |
F | C,D | 1 | 3 | 6 |
G | D,E | 1 | 3 | 14 |
H | F,G | 2 | 5 | 14 |
What is the critical path?
A-D-F-H
B-E-G-H
A-C-F-H
A-D-G-H This answer is Correct
What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
21.000 days
What is the probability of completing this project within 22 days?
Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.
The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D-F-H B-E-G-H A-C-F-H A-D-G-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. d. What is the probability of completing this project within 22 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started