The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A -- 4 B -- 5 C
The following represents a project with known activity times. All times are in weeks.
Activity | Immediate Predecessor | Time |
A | -- | 4 |
B | -- | 5 |
C | A | 3 |
D | B | 8 |
E | B | 2 |
F | C, D | 3 |
G | C, D | 7 |
H | E, F | 2 |
What is the minimum possible time required for completing the project, what is the latenst possilbe time that C may be started without delaying completing of the project, what is the slack time for D, and the finish time for F?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started