The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A - 4 B - 3 C

The following represents a project with known activity times. All times are in weeks.
Activity
Immediate
Predecessor
Time
A
-
4
B
-
3
C
A
2
D
B
7
E
C, D
4
F
B
5
Using the data in Table above, what is the minimum possible time required for completing the project?