The following six jobs are to be scheduled on a single machine: Job 1 2 3 4 5 6 Processing time ( min . )

The following six jobs are to be scheduled on a single machine:
Job 123456
Processing time (min.)80130210120150110
Suppose the jobs are processed in shortest processing time order. Compute the average flowtime after each job is completed. Round your answer to two decimal places.
a.401.67
b.391.97
c.416.67
d.422.67

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions

Question

Find x, y, z, and w. 1. 2. 3. 4. 3 3 y 1 4

Answered: 1 week ago