The following table contains information concerning jobs that are awaiting processing at a work center. JOB PROCESSING DUE TIME (hours) (hours) > W 8
The following table contains information concerning jobs that are awaiting processing at a work center. JOB PROCESSING DUE TIME (hours) (hours) > W 8 15 10 18 4 12 Y 4 10 Z 2 12 13 Sequence the jobs using First Come First Server (FCFS), Earliest Due Date (EDD) and Shortest Processing Time (SPT). Assume the list is by order of arrival. For each of the methods determine the Average Wait Time, Average Flow Time, and Average Tardy Time.